04 · ELECTRICAL & SAFETY

Electrical, Testing & Safety

Some of the most important work is invisible: an installation that is tested, documented and compliant. We test complete installations and resolve faults, design dedicated electrical boards, certify installations to utility, fire-service and insurer requirements, and manage connection upgrades.

Get a quote

Copper busbars and cable lugs in a main switchboard

04 · SIMULATOR

What do we test in an installation?

Pick a component in the diagram to see what is tested, with which instrument and what counts as a pass.

Diagram of an installation: meter, main board, RCD, final circuits, earthing and a solar system. Choose a component with the buttons.

RCD (30 mA)

Test
Trip time at the rated residual current (IΔn) and its multiples, plus a ramp test
Instrument
RCD tester
Pass criterion
Trips within 300 ms at IΔn, 150 ms at 2·IΔn and 40 ms at 5·IΔn
Reference
IEC 61008-1 · IEC 60364-6 · IEC 61557-6

Insulation fault demo

Current leaks to the metal enclosure of an appliance. What happens with and without an RCD?

Protection
Leakage current

When animated, the trip is slowed 40 times. Trip times are typical values for a healthy device, not measurements.

Maximum break time per the standard150 ms

Which connection size do you need?

120 kW
0.70
0.90
Calculated current135 A
Recommended connection3×160A

The final size is set with the utility based on a detailed design.

Preliminary engineering estimate — a binding design requires a site survey.

Assumptions
  • Criteria follow IEC 60364-6 and IEC 61008-1. The wording is illustrative and not a substitute for the standard.
  • Trip times in the demo are typical values for a healthy device.
  • Current calculation: three-phase 400 V.

04 · CAPABILITIES

What we do

Installation testing

Testing complete installations, finding and fixing faults, with a clear findings report.

Electrical boards

Dedicated boards designed for machines, plants and buildings.

Connections & utility

Connection upgrades and follow-through with the utility connections and inspection teams.

Safety

Certificates to fire-service and insurer requirements, and safe-work practice on every site.

04 · IN DEPTH

In depth

Anatomy of an installation: from the supply point to the socket

Every installation is a chain. The meter sits at the supply point; from there the supply runs to the main board and main breaker, then to the sub-boards, and from them to the final circuits that feed sockets, lighting and machines. The protective devices are coordinated so that the one nearest a fault trips first (selectivity), and a fault on one circuit does not black out the whole building. RCDs protect the final circuits.

The size of the utility connection follows from the current. Take the connected load, multiply it by the diversity factor, since not everything runs at once, and divide by √3, the line voltage and the power factor: I = P·1000·k ÷ (√3·400·PF), with P in kW. Round the result up to a standard connection size, 25 A to 630 A in the simulator; the final size is set with the utility. In the simulator above you can run this calculation, and pick a component in the diagram to see what is tested in it.

Voltage drop is limited by regulation too: under the Israeli final-circuits regulations (1984), regulation 2(e), the drop between the consumer’s terminals and any point of use in the installation must not exceed 3% of the nominal grid voltage. In a long or undersized cable the drop grows and equipment may run on too low a voltage, so it is checked at the design stage.

Sources: IEC 60364 series · Israeli Electricity (Final Circuits Supplied at up to 1000 V) Regulations, 1984

Anatomy of an installationFrom the supply point and meter, through the main breaker and the busbar, to two sub-boards. In the drawing, under one of them, three final circuits are protected by one 30 mA RCD; the device nearest a fault trips first. An earth electrode joins the main board’s own earth terminal, not the live busbar.

How an RCD saves lives

An RCD constantly compares the current going out on the phase with the current coming back on the neutral. Both conductors pass through a toroidal transformer, and as long as the two currents are equal, their magnetic fields cancel out. If part of the current does not come back, it is leaking to earth, possibly through a person. The difference creates a field in the toroid, and the device disconnects the circuit.

An RCD for personal protection has a rated residual current (IΔn) of 30 mA. Under IEC 61008-1 it must trip within 300 ms at IΔn, 150 ms at 2·IΔn and 40 ms at 5·IΔn, and it must not trip at half of IΔn or less, to avoid nuisance tripping. In Israel, the switchboard regulations (1991), regulation 29(d), require every final circuit in a dwelling to be protected by a 30 mA RCD. Press the test button from time to time to check that it trips.

A transformerless solar inverter can pass DC leakage current, so according to manufacturer data it needs a type B RCD or residual-current monitoring built into the inverter under IEC 62109-2. In TT earthing, IEC 60364-4-41 adds a rule: the earth resistance times the RCD’s rated residual current must not exceed 50 V, and in Israel the earthing regulations also limit the electrode resistance to 5 Ω at most. In the fault demo in the simulator above, you can inject a leak and see what happens with and without an RCD.

Sources: IEC 61008-1 · IEC 60364-4-41 · Israeli Electricity (Installation of Switchboards up to 1000 V) Regulations, 1991

How an RCD worksThe toroid compares the current going out on the phase with the current coming back on the neutral. Current that leaks to earth makes a difference, and an RCD trips on a residual current of at least 30 mA (its rated current). The maximum break time is 300 ms at the rated current, 150 ms at twice that and 40 ms at five times that.

Thermography: finding a fault before it burns

A loose connection or an overloaded component heats up before it fails. A thermal camera sees that heat without touching anything and without shutting the installation down. For the image to mean something, the board is scanned under load, at least 40% of its rating, and each component is compared with a similar one under the same load, such as the three phases of the same breaker.

Severity is graded by the rise over the similar component, per NETA table 100.18: 1–3 °C is a possible deficiency, 4–15 °C a probable one, and over 15 °C a major one. In the photo, from one of our inspections, a cable connection reached 96.8 °C while the average temperature in the same frame was 36.9 °C. It is one example from the field, not a statistic.

Thermography takes experience. Shiny copper emits little infrared radiation (it has a low emissivity), so it reads colder on the camera than it really is, and someone who does not know this can miss a hot spot. Solar modules have their own conditions under IEC TS 62446-3, for example an irradiance of at least 600 W/m² on the module plane. In the simulator above, clicking the main board shows thermography as part of its test.

Sources: ANSI/NETA MTS, table 100.18 · NFPA 70B-2023 · IEC TS 62446-3:2017

Thermography: compare with a similar partIn the drawing, three similar breakers under the same load, and the third is hotter than the other two. Per the NETA MTS temperature-difference guidance, measure the rise over a similar part: 1 to 3 °C is a possible deficiency, 4 to 15 °C a probable one, and over 15 °C a major one.
Thermal image: a 96.8 °C hot spot at a cable connection against a 36.9 °C average

04 · PROCESS

How it works

  1. 01

    Request & data

    Collecting drawings, requirements and the purpose of the test.

  2. 02

    On-site test

    Testing the installation by a licensed inspector.

  3. 03

    Report & findings

    A structured report with findings and recommendations.

  4. 04

    Repair & design

    Carrying out repairs or designing the required changes.

  5. 05

    Approval & handover

    Re-test and delivery of the certificates.

04 · CLIENTS

Who it is for

  • Factories and industrial buildings
  • Public buildings and institutions
  • Retail and offices
  • Contractors and developers

04 · FIELD

From the field

  • L1–L3 and N busbars in a switchboard
  • Motorised main breaker in a switchboard, labelled in Hebrew
  • Medium-voltage cable terminations in switchgear cells
  • Thermal image: a 96.8 °C hot spot at a cable connection against a 36.9 °C average
  • Thermal image of a healthy switchboard
  • Work on a medium-voltage pole from a bucket lift
  • Cable work at night
  • Trenching for a cable route at night

04 · FAQ

Frequently asked questions

How often should an installation be inspected?

The regulations set when an installation needs a periodic inspection, and how often, by the type of installation and its use, and the inspection itself is done by a licensed electrical inspector. For large switchboards we recommend adding periodic thermography, because it finds loose connections and overloaded components before they cause a fault. We can check what applies to your installation.

What is the difference between an RCD and a circuit breaker?

An RCD protects people: it detects leakage current, current escaping to earth, possibly through a person, and disconnects within a fraction of a second. A circuit breaker protects cables: it trips on overload and short circuit, so that the cable does not overheat and start a fire. The two complement each other, which is why an installation needs both.

Why does the RCD keep tripping?

An RCD trips when it detects leakage current. The cause can be a real leak, such as moisture, damaged insulation or a faulty appliance, or several small leaks from different appliances adding up. Either way, never bypass or disable it: it is the protection against electric shock. Call an electrician, who can find the source by measurement.

How do you know what utility connection size you need?

Start from the connected load of everything in the building, multiply by a diversity factor, since not everything runs at once, and allow for the power factor. The current per phase is I = P·1000·k ÷ (√3·400·PF), with P in kW, rounded up to a standard connection size. The simulator above lets you change the inputs and see the current and the recommended size. The final size is set with the utility, based on a detailed design.

CONTACT

Want to hear more?

Leave your details and we will come back with a proposal that fits your site.

For example 050-123-4567

Submitting this form is subject to our privacy policy